A semiconductor fab, or a new phase of one, from the business case and technology choice through site selection, permits and incentives, facility design, construction, cleanroom and facility systems, tool procurement, installation and qualification, process transfer and first wafers to the yield and capacity ramp, operations and continuous improvement, and expansion or end of life. The output is a qualified factory running customer wafers.
Fab build and equipment qualification lifecycle: 12 stages and 20 gates, from Business Case & Technology Choice to Expansion & End of Life.
12 stages and 20 gates, 3 of the gates technical readiness reviews (TR). Each stop opens its stage; each sign opens its gate. Point at a stop or tab to it to read what the stage is for. What the codes mean
In collaboration with The Digital Electronics Blog (opens in a new tab)
A dashed sign with a TR tag is a technical readiness review gate.
In collaboration with The Digital Electronics Blog (opens in a new tab)
Deciding whether a new fab or a major fab phase is worth building: the demand it serves, the process technologies and wafer size it will run, the capacity and product mix, the wafer cost it must reach and the capital it needs, ending in an approved business case that funds site selection and design.
Investment concept approval gateTechnology and capacity choice gateTR1, technical readiness reviewBusiness case approval gate
Finding and choosing where the fab will stand, weighing energy supply, water, skills and workforce, transport and industrial infrastructure, supply chain security, natural hazard exposure, sustainability and the public incentives on offer, and closing on land and an agreed site.
Securing the permits a fab needs to be built and to operate, such as land use, building, environmental, air, water discharge and hazardous materials permits, completing the environmental impact assessment and community engagement, and negotiating and signing the public incentive agreements and their conditions.
Turning the tool list and capacity plan into a facility design: the basis of design, the layout of fab, sub-fab and support buildings, the cleanroom, utility, gas, chemical, exhaust and abatement systems, automation and security, then the detailed design, the construction cost estimate and the final investment decision.
Building the fab: site preparation, foundations and the vibration-controlled structure, the building shell and envelope, and the central utility and support buildings, managed for safety, quality, cost and schedule until the building is enclosed and ready for cleanroom fit-out.
Fitting out the cleanroom under clean build protocol and installing and commissioning the facility systems: air handling and filtration, ultrapure water, bulk and specialty gases, chemical distribution, process cooling, vacuum, exhaust, abatement and waste treatment, electrical power and backup, until the cleanroom is certified to its cleanliness class.
Buying the process, metrology and automation equipment and the materials the fab will run on, with long-lead tools ordered early, then sequencing deliveries, moving tools into the cleanroom and setting them in their bays without damage or contamination.
Connecting each tool to its utilities, starting it up, running the supplier's acceptance tests against the purchase specification, signing off its safety, linking it to factory automation and qualifying it on wafers, including matching to reference tools, until the tool set is ready to run the process.
Bringing the process to the new fab, either copied from a source fab or developed for it: transferring recipes and specifications, running short loops and full-flow lots, getting the first wafers out, and proving the process at the new fab matches its reference in results and reliability.
First wafers out gateProcess qualified at the new fab gateTR3, technical readiness review
Starting production for customers and raising wafer starts, equipment availability and yield to the levels in the plan, with customers qualifying their products at the new fab, statistical process control in place and the construction project formally closed and handed over to operations.
Production start gateRamp complete gateProject close-out gate
Running the fab day to day and improving it: process control and excursion response, maintenance and equipment availability, cycle time, cost, energy, water and emissions reductions, tool upgrades and process changes under change control, workforce development and the reports incentive agreements require.
Deciding what comes next for the fab: adding a phase or shell space, converting it to a new technology, or winding it down, and when it closes, transferring customers and products, removing or reselling tools, decontaminating the facility, remediating the site and meeting the exit terms of permits and incentive agreements.
Expansion or exit decision gateDecommissioning complete gate
The full lifecycle detail, with its charts, flows, tables and every section, is for registered members. Registration is free and takes a minute. You come back to this page afterwards.